[edit] Aim and benefits
Deliver whole life value by orienting design and specification to a life cycle approach.
Early stage understanding of the likely construction of the building and its servicing strategy, focuses the design team on likely requirements for service risers, ceiling void depth etc.especially for conditioned buildings requiring large amounts of plant. This can draw attention to the overall size requirements of the building and its projected costs, which may lead to alternative means of construction.
[edit] When to consider
At the earliest stage. Elemental level has to be completed before the end of RIBA Stage 2 and component level has to be completed before RIBA Stage 4.
[edit] Step-by-step guidance
Ensure all project team members are aware that there is a time restriction on the achievement of this issue. Therefore, it is important to define RIBA stages at the earliest opportunity and communicate them to all parties involved.
[edit] Questions to ask while seeking compliance
- Is a compliant ISO 15686 life cycle cost (LCC) study available?
- Does the design team have any experience of undertaking a BREEAM compliant LCC on any previous projects, can their experiences be shared with the o/a project team?
- Do they already have any templates that they can use?
- Are there any particular construction processes that lend themselves to favourable life cycle outcomes?
[edit] Tools and resources
Guidance on a compliant LCC analysis can be found in PD 156865:2008 Standardized method of life cycle costing for construction procurement - a supplement to BS ISO 15686-2:2008 Buildings and constructed assets, service life planning - Part 5.
PD 156865: 2008 is often quite a difficult document to get hold of. Ask the team if they have any extracts, search the Wiki for compliance details?
[edit] Tips and best practice
Collaboration between the quantity surveyor (QS), architect and energy assessor at the early stage of the design development would allow calibration of the design for a efficient and cost-effective solution.
[edit] Typical evidence
[edit] Design stage
- RIBA Stage 2 and RIBA Stage 4 reports from costing specialist.
- LCC Report.
- File notes from the project team demonstrating how the LCC study impacted design decisions etc.
[edit] Post construction
- Letter of confirmation from the developer/contractor showing that the lowest LCC option (as selected at design stage) has been implemented.
[edit] Applicable Schemes
The guidelines collated in this ISD aim to support sustainable best practice in the topic described. This issue may apply in multiple BREEAM schemes covering different stages in the life of a building, different building types and different year versions. Some content may be generic but scheme nuances should also be taken into account. Refer to the comments below and related articles to this one to understand these nuances. See this document for further guidelines.
- UK New Construction 2014
- UK RFO 2014 (just check that the requirements are slightly different to NC)
BRE Global does not endorse any of the content posted and use of the content will not guarantee the meeting of certification criteria.
--Multiple Author Article 16:21, 19 Apr 2018 (BST)
[edit] Related articles on Designing Buildings Wiki
- BREEAM Life cycle impacts.
- BREEAM.
- Building Back Better: Circularity and BREEAM.
- Building back better with BREEAM.
- Component level life cycle cost options appraisal.
- Design life.
- Elemental life cycle cost plan.
- Integrated Material Profile and Costing Tool.
- Life cycle assessment.
- Life cycle costing.
- Life Cycle Costing BG67 2016.
- Life cycle inventory.
- One Click LCA.
- Reference service life.
- RIBA stages.
- Service life.
- Service life of products.
- Whole life costs.
- Whole-life value.
Featured articles and news
About the 5 Percent Club and its members
The 5% Club; a dynamic movement of employers committed to building and developing the workforce.
New Homes in New Ways at the Building Centre
Accelerating the supply of new homes with MMC.
Quality Planning for Micro and Small to Medium Sized Enterprises
A CIOB Academy Technical Information sheet.
A briefing on fall protection systems for designers
A legal requirement and an ethical must.
CIOB Ireland launches manifesto for 2024 General Election
A vision for a sustainable, high-quality built environment that benefits all members of society.
Local leaders gain new powers to support local high streets
High Street Rental Auctions to be introduced from December.
Infrastructure sector posts second gain for October
With a boost for housebuilder and commercial developer contract awards.
Sustainable construction design teams survey
Shaping the Future of Sustainable Design: Your Voice Matters.
COP29; impacts of construction and updates
Amid criticism, open letters and calls for reform.
The properties of conservation rooflights
Things to consider when choosing the right product.
Adapting to meet changing needs.
London Build: A festival of construction
Co-located with the London Build Fire & Security Expo.
Tasked with locating groups of 10,000 homes with opportunity.
Delivering radical reform in the UK energy market
What are the benefits, barriers and underlying principles.
Information Management Initiative IMI
Building sector-transforming capabilities in emerging technologies.
Recent study of UK households reveals chilling home truths
Poor insulation, EPC knowledge and lack of understanding as to what retrofit might offer.